From engineering feasibility to integrated system delivery.
For Pilot & Demonstration Plants and Industrial Process Skids, we work in three phases: Basic Engineering & Feasibility, Detailed Engineering and Integrated Design & Build. Engage us for one phase or several, with no obligation to continue.
Industrial Automation and PlantON™ projects follow their own delivery steps, shown on those pages.

Understanding the requirement
Every Process Skid Plant project starts with the application.

- Process and operating requirementsObjectives, materials, operating conditions, capacity and major equipment.
- Project stageConcept, pilot, demonstration, detailed engineering or industrial implementation.
- Technical and site interfacesEquipment, instruments, automation, utilities and facility interfaces.
- Available engineering informationProcess documents, test data, calculations, drawings and specifications.
- Expected outcomeThe deliverables and decisions the engagement must produce.
From this, we agree the right phase and scope.
See the engineering approachCapabilities & context
The three engagement phases
Each phase has its own objectives, deliverables and acceptance criteria. Engage us for one phase or several.
01 · Basic Engineering & Feasibility
What it does
Turns a lab result, process idea or upgrade need into a defined engineering basis and a Class 4 budgetary estimate, before you commit to detailed design or hardware.
Best when
The process works at lab scale or the requirement is still forming, and you need a budget basis or a go/no-go for the next investment decision.
Decision it enables
Proceed to Detailed Engineering, run further evaluation, or revise the concept.
Typical deliverables
- Process description and design/operating basis
- Requirements review and open-questions register
- Preliminary PFD and heat & mass balance, where process data allows
- Preliminary P&ID
- Preliminary equipment list and utility requirements
- Preliminary instrumentation and automation requirements
- Process and equipment option assessment
- Preliminary layout and footprint
- Interface, risk and safety-issue review
- Long-lead items and preliminary schedule
- Class 4 budgetary estimate (AACE)
- Recommendation for the next decision
02 · Detailed Engineering
What it does
Develops the agreed basis into a coordinated, procurement-ready engineering package, priced to a Class 2 estimate.
Best when
The process basis is settled and you need a buildable package: for your own fabrication, for a tender, or for a build phase with us.
Outcome
A package ready to tender or build. Then: proceed to Integrated Design & Build with us, engage another execution partner, or revise the package.
Typical deliverables
Process & mechanical design
- PFDs and P&IDs
- Line list
- Equipment data sheets
- Skid layout, general arrangement and 3D coordination
- Piping and mechanical drawings within the agreed scope
Instrumentation selection
- Instrument specifications and data sheets
- Instrument and valve lists
- I/O list
Electrical design
- Single-line diagram
- Load list
- Cable schedule
- Panel GA and wiring diagrams
Control narrative & architecture
- Control philosophy and sequences
- Alarm/interlock and cause-and-effect definition
- Control system and network architecture
Procurement, safety & cost
- Procurement specifications and RFQ packages
- FAT/SAT plan and acceptance criteria, agreed before hardware is bought
- HAZOP support and safety-review input
- Class 2 cost estimate (AACE) and agreed decision package
03 · Integrated Design & Build
What it does
One accountable team engineers, procures, fabricates, supplies instrumentation and electrical works, programs, integrates and tests the contracted system, followed by defined site support and handover.
Best when
You want one partner responsible from drawings to a working system.
Outcome
A system accepted against the criteria agreed at the start.
Typical deliverables
Procurement & fabrication
- Procurement, expediting and vendor document review
- Skid fabrication and assembly
- QA/QC and inspection records
Instrumentation
- Instrument supply and installation
- Calibration and loop checks
Electrical
- Control and power panels
- Field wiring and cabling
Automation & data
- PLC/HMI/SCADA programming
- Data architecture, with optional PlantON™ connection
Testing, commissioning & handover
- FAT, with scope agreed per project
- Installation supervision, SAT and commissioning support
- Operator training
- As-built drawings, O&M manuals, spare parts list and handover
The exact deliverables are agreed for each engagement. Cost estimates are classified to AACE International guidelines: Class 4 at feasibility, Class 2 at detailed engineering.
Each phase is a separate paid scope. You can stop, change direction or engage another partner after any phase.
Delivery logic
From the first conversation to a clear next step.
- 01Understand the project
- 02Define the scope, phase and deliverables
- 03Execute and review against acceptance criteria
- 04Decide the next step
Safety by design
Safety is a design input, not a commissioning fix.
Pilot and process systems often combine unfamiliar chemistry, new operating windows and a scope that keeps changing. We manage that risk across process, mechanical, electrical and controls disciplines from the first phase.
01 · Identify hazards early
Identify process hazards and credible deviations early, through the risk-review method agreed for the project.
02 · HAZID and HAZOP
Support and take part in HAZID and HAZOP reviews, or other formal reviews, where they suit the scope and stage.
03 · Safeguards into the design
Turn each agreed safeguard into equipment, relief and venting, isolation, alarm, permissive and interlock requirements.
04 · Safe operating states
Define safe start-up, shutdown, purge and preparation, and behavior on loss of utilities, as the process requires.
05 · Verify before handover
Check the implemented safeguards at design review, factory acceptance (FAT) and site acceptance (SAT).
HAZOP support, alarm and interlock definitions, FAT and SAT plans and commissioning procedures sit in the phase deliverables above, where the project scope calls for them.
Start with what you know
For an effective kickoff
The first discussion is most useful when the team can share its existing basis, open questions, and the next decision the project must enable.
Prepare a technical enquiry- Scientific or operating objective and present project maturity
- Existing process information, drawings and test evidence
- Who owns equipment, facilities, EHS and site interfaces
- Budget stage, next decision date and approval stakeholders